29/6/1999 | Keel laid |
7/5/2001 | Christined by Mrs Camilla Nylung on HDW shipyard. |
7/5/2001 | Delivered |
5/2001 | Hanko – Rostock route |
17/4/2006 | Hanko – Paldiski – Rostock route |
7/6/2006 | Hanko – Rostock route |
9/1/2007 | Tallinn – Helsinki – Rostock route |
1/9/2008 | Helsinki – Rostock route |
3/1/2010 | Refurbished on Kopli, Estonia |
26/4/2010 | Helsinki – Rostock route |
26/12/2010 | Helsinki – Tallinn route |
31/12/2010 | Laid up |
1/4/2011 | Helsinki – Rostock route |
7/3/2011 | Three years charter contract to Stena Line |
15/8/2011 | Last day on Tallink service, arrived to Muuga. |
8/2011 | Delivered to Stena Line |
21/8/2011 | Arrived to Remontowa ,Gdansk for renovation work. |
22/11/2011 | Belfast – Cairnryan route |
27/11/2011 | Suffered thruster problems last night and damaged a propeller when attempting to berth at Belfast in high winds |
| Repaired at Harland and Wolff |
9/1/2012 | Two departures cancelled due to technical reasons. |
2/2013 | Two weeks drydocking at Harland & Wolff |
5/2/2014 | Stena Superfast vessels charter agreements extended to 2019 |
15-17/2/2014 | Maintenance work |
22-25/3/2014 | Maintenance work |
9/12/2014 | Hit a pier at Cairnryan port |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |